I-15 Limonite Interchange Project
Project update for the week of February 10 - 16, 2019
Limonite Progress Schedule
Construction will focus on stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.
Lane and Ramp Closures
No closures anticipated this week.
For full construction notice click here.